How To Calculate Capacity In Agile

Agile Capacity Formula:

\[ Capacity = Sprint\ Days \times Team\ Members \times 6-8\ hours/day \times 80\%\ buffer \]

days
members

Unit Converter ▲

Unit Converter ▼

From: To:

1. What Is Agile Capacity Calculation?

Agile capacity calculation helps teams estimate how much work they can complete during a sprint. It considers available working days, team size, daily productive hours, and accounts for various interruptions with an 80% buffer.

2. How Does The Calculator Work?

The calculator uses the agile capacity formula:

\[ Capacity = Sprint\ Days \times Team\ Members \times 6-8\ hours/day \times 80\%\ buffer \]

Where:

Explanation: The formula provides a realistic estimate of available working hours by accounting for typical productivity loss in agile environments.

3. Importance Of Capacity Planning

Details: Accurate capacity planning helps teams commit to achievable sprint goals, prevents overcommitment, improves velocity tracking, and ensures sustainable pace for team members.

4. Using The Calculator

Tips: Enter the number of working days in your sprint, the number of team members, and select the average productive hours per day (typically 6-8 hours). The calculator automatically applies an 80% buffer for realistic capacity estimation.

5. Frequently Asked Questions (FAQ)

Q1: Why use an 80% buffer in capacity calculation?
A: The 80% buffer accounts for meetings, interruptions, administrative tasks, and unexpected issues that reduce productive coding time in agile environments.

Q2: How many productive hours should I estimate per day?
A: Typically 6-8 hours per day, depending on your team's meeting schedule, support responsibilities, and work environment.

Q3: Should we include part-time team members in the calculation?
A: Yes, but adjust their contribution proportionally (e.g., a half-time team member counts as 0.5).

Q4: How does capacity relate to velocity?
A: Capacity is the available hours, while velocity is the amount of work actually completed. Comparing them helps teams improve estimation accuracy.

Q5: Should we adjust capacity for new team members?
A: Yes, new team members typically have lower capacity initially as they ramp up on the codebase and processes.